NEWPORT BEACH CITY MANAGER UPDATE:

DREDGING PROJECT

BY GUEST CONTRIBUTOR GRACE LEUNG, NEWPORT BEACH CITY MANAGER – JANUARY 31, 2025

Source: Newport Beach Independent – https://www.newportbeachindy.com/newport-beach-city-manager-update-dredging-project-nbpd-mobile-cafe/

Grace Leung, Newport Beach City Manager

Grace Leung, Newport Beach City Manager

The long-awaited dredging project for lower Newport Harbor will move forward, following recent approval by the Newport Beach City Council and Port of Long Beach to use dredged sediment for a pier fill project at the port.

This arrangement is similar to Newport Beach’s previous projects in 2011 and 2012, when dredged sediment from Newport Harbor that was unsuitable for open ocean disposal was transported to Long Beach for the Middle Harbor Redevelopment Project.

A port fill option was not available when the City and Army Corps of Engineers began designing plans for the upcoming phase of dredging in Newport Harbor. The City’s proposed solution, known as confined aquatic disposal, will no longer be required. Now, up to 225,000 cubic yards of dredged material will be transported by barge to the Port of Long Beach, and the remaining material will be placed in a federally approved open ocean site.

This dredging project, which removes accumulated sediment from the harbor floor, is critical to maintain the navigational safety and the environmental health of Newport Harbor.

The Army Corps of Engineers is expected to begin dredging within the next few months.


Source: Newport Beach Independent – https://www.newportbeachindy.com/newport-beach-city-manager-update-dredging-project-nbpd-mobile-cafe/

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *

Newport Harbor Pirates Cove

Newport Beach, known for its pristine beaches and picturesque harbors, has long been committed to preserving its natural resources. To further increase the City’s ability to monitor and maintain water quality in Newport Harbor, the City’s Harbor Department recently deployed two state-of-the-art water quality sensing buoys, or DataPods, in the harbor.

The Newport Bay Conservancy is hosting Coastal Cleanup Day at Upper Newport Bay on Saturday, Sept. 23 from 9 a.m. to noon.

Volunteers will meet at a dozen different mini-cleanup day sites around the 11-mile bay including the Peter and Mary Muth Interpretive Center, Newport Aquatic Center, Big Canyon, Vista Point, Jamboree Bridge, etc. Exact meeting location will be announced and sent to everyone (group leaders) prior to Sept. 21.

Join Nancy Gardner as she chats with former Harbor Commission Chair Bill Kenney and Senior Civil Engineer John Kappeler about the upcoming Newport Beach water wheel project.

The Balboa Island Ferry, one of our most iconic Newport Beach tourism experiences, could be no more.

If that sounds dramatic, it is. I can’t imagine our city without the ferry, but unless something is done, this treasured piece of our city could be gone in less than two years.

Thousands of locals and visitors use the ferry every year and it’s a vital part of our culture and history. It is part of what makes us Newport Beach, and in my mind, it is as important as our beaches. But all of that is now threatened and could be lost.

More than 70 boats competed in the 87th Annual Flight of Newport Beach, presented by the Commodores Club of the Newport Beach Chamber of Commerce with assistance from the Balboa Yacht Club.

Initially known as the Flight of the Snowbirds and later the Flight of the Lasers, the Flight of Newport had three different classes of boats racing to circumvent Newport Harbor.