(Tribune News Service) — All permits are in place for the U.S. Army Corps of Engineers to dredge channels in Lower Newport Bay and bury any contaminated sediment in a massive underwater pit at the heart of Newport Harbor.

But the project is now facing multiple legal challenges that could slow it down or thwart it entirely, as resident and environmental groups that tried to block those permits cite ongoing concerns over risks to marine life and bay contamination.

Already, work on the project is progressing slower than expected. And while efforts to clear sediment brought into channels by tides, boats and storms were expected to start last fall, the Army Corps hasn’t yet put the project out to bid.

“We had anticipated being further along at this point,” said Chris Miller, a manager with Newport Beach’s Public Works department who’s been overseeing the project. He cited standard processes on the Corps’ side to wrap up construction documents as reason for the delay.

Opponents aim to argue in court that those plans still don’t include sufficient analysis and safeguards to protect Newport Harbor.

Friends of Newport Harbor, a coalition of seaside residents that includes tech billionaire Palmer Luckey, sued the California Coastal Commission and the city of Newport Beach in late November over the project. Their lawsuit, filed in Orange County Superior Court, alleges the commission and city violated the Coastal Act and California Environmental Quality Act by approving the plan. A hearing on the case is set for July 11.

“This isn’t a problem solved. This is just sweeping the problem under the rug,” said Shana Conzelman, a Lido Island resident and volunteer director with Friends of Newport Harbor, of plans to bury contaminated sediment in the harbor.

The resident group also sued the Army Corps in federal court in late February for failing to respond to requests for public information. They said in a statement that they “refuse to allow the Corps’ stonewalling to rob us and other concerned residents of Orange County of our right to oppose this environmentally disastrous project, both in court and through grass-roots political efforts.”

Shortly after that suit was filed, Conzelman said they received some information from the Army Corps and Newport Beach, but not all of the documents they’d requested. She said her group is working with three different law firms and considering additional legal action.

A third suit will likely come from the environmental group Orange County Coastkeeper. On Jan. 5, the organization sent written notice to the Army Corps and heads of other federal agencies about plans to sue in 60 days if additional studies weren’t completed to see how the project could affect endangered and threatened species in the area, including green sea turtles.

That 60-day window expires this weekend. As of Wednesday, Matt Sylvester with Orange County Coastkeeper said they hadn’t heard back from the federal agencies.

This project has been in the works for more than four years.

The Army Corps received permits in early 2022 to clear 879,900 cubic yards of material from navigational channels in Lower Newport Harbor that could pose problems for some 10,000 vessels based there. But before dredging could start, Newport Beach needed a permitted plan in place to deal with any contaminated material crews dig up.

Testing indicated most material in the dredging area was clean enough for ocean disposal, at a site six miles offshore. However, some 112,500 cubic yards of sediment showed elevated levels of mercury and industrial chemicals such as DDT.

The city’s solution calls for digging a hole 590 feet wide, 590 feet long and 46 feet deep in the center of the lower harbor, directly between Bay Island, Lido Isle and Harbor Island, to create what is termed a confined aquatic disposal pit, or CAD. Crews then would take contaminated sediment from the channels, drop it in the 8-acre pit and cover it with a layer of clean sand.

Eventually, the city plans to have three feet of clean sand as a barrier. But first, city leaders saw an opportunity to give harbor residents and businesses — who often ask to dredge around their own properties to add docks or other facilities — an option to add their own sediment to the CAD. So for at least two years, until material from those other projects gets added to the pit, the CAD will be capped with just one foot of clean sand.

Having such a thin layer of sand between boat anchors and contaminated sediment in water 20 feet deep worries residents and environmental groups. They’ve also flagged how plumes of sediment might contaminate surrounding waters as the material is dumped into the CAD. So they asked regulators to consider alternatives, such as moving the material to land where it can be isolated or cleaned up.

Test results, checking for sediment contamination, were originally valid through the end of 2022. But Miller said regulators approved an extension so they could keep the project moving forward.

“There have not been any significant events since we tested, so there isn’t any real reason to suspect that it has changed,” Jim Fields, project manager with the Army Corps’ Los Angeles District, said Wednesday.

Field said the agency now plans to put the contract out to bid on March 23 and hopes to finish work in fall 2024.


©2023 MediaNews Group, Inc.

Source: Stars And Stripes Legal challenges loom as plans to dredge Newport Harbor, bury contaminated sediment inch forward

Visit ocregister.com.

Distributed by Tribune Content Agency, LLC.

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *

Newport Harbor Aerial

The Newport Beach City Council approved an agreement with a firm for federal advocacy services related to harbor dredging efforts and programs, Feb. 27. Carpi & Clay was retained to represent Newport Beach at the federal level in hopes the firm would help bring the city’s issues to the forefront when it comes to harbor dredging.

“The city has been actively working with the U.S. Army Corps of Engineers … and to a limited extent, federal elected representatives, to present and educate them on our dredging needs in Newport Harbor, as well as to get our project on the Corps’ upcoming project funding list,” city staff told council members in a report. “Keeping our project in focus and on the recommended funding list of both the Corps and the many elected representatives that need to review and approve it is, and continues to be, a significant challenge particularly because we do not have a presence in Washington, D.C.”

An Army Corps study in 2017 revealed there is about 650,000 cubic yards of sediment remaining in federal waters and must be dredged to “maintain adequate navigation.”

Continue reading at The Log…

Mayor Marshall "Duffy" Duffield

By Devon Warren

Inventor of the electric Duffy boat addresses his plans to improve the Newport Beach Harbor as city’s new mayor.

NEWPORT BEACH — In the efforts to track down Marshall “Duffy” Duffield, the new mayor of Newport Beach, it seemed quite ominous his reply to an email correspondence about scheduling an interview stated, “I’m around,” with his phone number attached.

The Duffy name is certainly “around” in many corners of Newport Beach Harbor, as it’s literally everywhere you turn – in the form of a “Duffy” electric boat.

As a long-time Newport Beach resident (more than 50 years) and the inventor of the electric boat bearing his name, many of us would consider Duffield the quintessential image of the dreamy Southern California yachting life.

A car insurance agent once told me we pay such catastrophic prices because “it’s a privilege to live” in Southern California. In a lot of ways, Duffield has taken such privilege and created an empire from it – him, and most other residents of California’s coast, live in a Technicolor world of scenic beauty that others across the country may never see in their lifetimes.

Continue reading at TheLog.com…

Harbormaster Vessels

The mooring management and harbor operations shift from Orange County Sheriff’s Department to the city of Newport Beach has been a fairly smooth transition as Harbormaster Dennis Durgan assumes his role.

Durgan took over the responsibility of overseeing more than 1,200 moorings from the Sheriff Department’s Harbor Patrol Division in July, with Newport Beach hiring 13 part-time harbor workers and obtaining two additional vessels.

The amount of foot traffic coming into Marina Park, where Durgan’s office is located, after the operational shift in management was unexpected.

Continue reading at The Log…