Lower Newport Bay’s main channel (the harbor) has not been dredged to its required 25-foot “design depth” since 1938. Our harbor is the primary economic, recreational and water quality resource asset in Newport Beach.

We haven’t had the money or political will to dredge the harbor’s main channel to its federally required design depth, until now.

As part of the U.S. system of waterways, Newport Harbor’s dredging is ultimately the responsibility of the federal government.

But we are in competition for federal funds with the nation’s major ports and naval bases.

Finally, after decades of lobbying, we are receiving nearly $16 million in dredging funds thanks to the hard work of Representatives Michelle Steel and Ken Calvert.

With funding in the bank, it’s now the city’s job to deliver a dredging plan that passes regulatory muster with the multitude of agencies that must approve the project. As the former Harbor Master, I can attest to the fact that the actual dredging will take less time than the permitting process.

We are at an inflection point in this critical process.

Dozens of Harbor Commission and City Council meetings with robust public input have resulted in a certified Environmental Impact Report It lays out a plan to bury and cap nominally contaminated dredge material (sand) in a hole between Lido and Bay Islands. It’s the same process used across the U.S. since the 1980’s to decommission landfills.

At last week’s city council meeting, the council majority agreed to allow an open-end third-party review of the City’s approved dredge project and one advanced by well-intentioned Lido Island residents.

This 11th hour review is a bad idea. It jeopardizes the federal funding and scheduling of the multi-million dollar dredging project for Newport Harbor.

A delay for an independent third-party review could set this whole project back years by putting a halt to all the momentum the process has at this time.

This in turn could make the cost rise substantially if the City could get it back on track with the Federal and State governments dredging contractor.

Our window to dredge is open now. Confusing state, local and federal agencies will close it.

Dennis Durgan / Chairman, Newport Harbor Foundation and Former Newport Beach Harbor Master

This letter first appeared in the Newport Beach Independent…

NB Harbor Department Parimal M. Rohit photo credit

The city of Newport Beach, steadily considered a premier boating destination, has made strides, in the last year, to improve services, amenities and educational information available to recreational boaters, residents and tourists. A model was also introduced for a freshly conceived Harbor Department, which also happens to be “new to the world,” according to several city officials.

“A lot has happened/is happening with harbor operations over the past year,” Tara Finnigan, Deputy City Manager, said in an email to The Log. “A lot of thought and effort went into the department structure that the city council approved on June 12.”

In addition to approving the department structure, council members approved the new budget of $1.1 million – up around $200,000 from last year’s budget – to be included in the 2018-19 fiscal year at the June 26 meeting.

Continue reading at The Log…

Photo Credit: Devon Warren/The Log

Newport Harbor Aerial

The Newport Beach City Council approved an agreement with a firm for federal advocacy services related to harbor dredging efforts and programs, Feb. 27. Carpi & Clay was retained to represent Newport Beach at the federal level in hopes the firm would help bring the city’s issues to the forefront when it comes to harbor dredging.

“The city has been actively working with the U.S. Army Corps of Engineers … and to a limited extent, federal elected representatives, to present and educate them on our dredging needs in Newport Harbor, as well as to get our project on the Corps’ upcoming project funding list,” city staff told council members in a report. “Keeping our project in focus and on the recommended funding list of both the Corps and the many elected representatives that need to review and approve it is, and continues to be, a significant challenge particularly because we do not have a presence in Washington, D.C.”

An Army Corps study in 2017 revealed there is about 650,000 cubic yards of sediment remaining in federal waters and must be dredged to “maintain adequate navigation.”

Continue reading at The Log…